Sunrise Power Plant Project - Main Page
[ California picture montage ]

PROJECT INFO

Project Fact Sheet

Project Location (Maps)

Project Photos

COMPLIANCE
PROCEEDINGS

Includes amendment to change project adding Phase II 265 MW combined cycle facility.

Announcements, Documents,
Notices & Other Info
Relating to the
Compliance Proceeding

(Updated: 5/12/03)

Docket Logs
98-AFC-4C
ORIGINAL
PROCEEDINGS


Notices, Orders,
Hearings & Workshops

(Updated: 8/22/01)

Documents,
Decisions and
Transcripts

(Updated: 2/8/01)

Docket Logs
98-AFC-4
Schedule
For This Case


Proof of
Service List


List of
Reviewing Agencies

Commission
News Releases


PARTICIPATION

Public Adviser's Office

Guide to
Public Participation
In Siting Cases


Overview of
Siting Process


Title 20
Calif. Code of Regulations


Commission
Siting Division


Acronyms
Used in Siting Cases



  SUNRISE
POWER PLANT PROJECT

Docket Number: 98-AFC-4C (Compliance proceeding of Application For Certification)


ANNOUNCEMENTS


To Be
Announced

Also see our
Energy Calendar

 

Key Dates
  • November 19, 2001 - Commission approves modification to add Phase II combined cycle power plant.
  • June 26, 2001 - Single cycle peaker portion of project goes on line.
  • May 14, 2001 - Amendment to Commission decision filed to modify (aka Phase II or "Sunrise II") into a combined cycle power plant, adding approximately 265 megawatts.
  • December 6, 2000 - The Energy Commission certifies the Sunrise Power Project.
  • November 20, 2000 - Revised Presiding Member's Proposed Decision (PMPD) issued.
  • October 26, 2000 -- Energy Commission staff files Supplemental Final Staff Assessment for the Sunrise Power Project (Sunrise).
  • September 12, 2000 -- Applicant files amendment changing the project from a facility to a simple-cycle, peaking facility.
  • May 8, 2000 -- Presiding Member's Proposed decision is released.
  • October 1, 1999 -- Energy Commission issues Part I of its Final Staff Assessment (FSA).
  • August 28, 1999 -- San Joaquin Valley Unified Air Pollution Control District Issues its Preliminary Determination of Compliance (PDOC).
  • August 2, 1999 -- Energy Commission issues its Preliminary Staff Assessment (PSA).
  • February 17, 1999 -- Energy Commission determines that the AFC is data adequate.
  • December 21, 1998 -- Application For Certification (AFC) filed by project proponent.

General Description of Project (updated 3/25/02)

The Sunrise Power Project is located approximately 35 miles southwest of Bakersfield, and one mile southwest of the intersection of State Route 33 and Shale Road in Kern County. The original Sunrise Cogeneration and Power Project application for certification was filed with the Energy Commission in 1998 for a cogeneration facility that would generate electricity for sale and produce steam for use in the adjacent oilfields in thermally-enhanced oil recovery processes. In September 2000, the applicant modified the cogeneration project to a simple-cycle peaking power project ("Sunrise Power Project") to deliver 320 MW of power for the peak demand of summer 2001. The simple-cycle Sunrise Power Project was certified on December 6, 2000, construction began on December 7, 2000, and commercial operation commenced on June 26, 2001.

On May 14, 2001, the Sunrise Power Company filed a petition to convert the simple-cycle power plant to a combined-cycle power plant (aka "Sunrise II"). This expansion will add approximately 265 MW of generating capacity, resulting in a nominal 585 MW combined-cycle power plant. In accordance with Executive Order D-25-01 of the Governor of the State of California, dated February 8, 2001, the petition was processed as a project amendment rather than as a new application for certification. The Energy Commission approved the petition on November 19, 2001, and construction on Sunrise II commenced on December 21, 2001.

Sunrise II will include two duct-fired heat recovery steam generators (HRSG), one 265 MW steam turbine generator (STG), an anhydrous ammonia selective catalytic reduction system to control air emissions, an evaporative condenser cooling tower system, a 15.5 mile water line, an expansion of the existing power plant site, and injection wells for wastewater disposal. The conversion to combined-cycle operations will provide baseload and peaking power up to 24 hours per day, seven days per week. Both generating and fuel efficiencies will be substantially improved through combined-cycle operations by more complete utilization of the combustion turbine generator's hot gases to generate steam in the HRSGs for added steam cycles and increased electrical output from the new STG.


Project Status

Sunrise I went on line June 27, 2001. Sunrise II is currently under construction and is scheduled for commercial operation in summer 2003.

More Information, Please Contact,

Chris Davis
Project Compliance Manager
Siting, Transmission and Environmental Protection Division
California Energy Commission
1516 Ninth Street, MS-2000
Sacramento, CA 95814
Phone: 916-654-4842
E-mail: CMDavis@energy.state.ca.us

For Questions About Participation In Siting Cases Contact:

Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PublicAdviser@energy.state.ca.us

News Media Please Contact:

Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us



| Homepage | Commission Info | Licensing Main Page | Calendar | Site Index | Search Site | Links | Contact Us |

Page Updated: November 17, 2003