Project Proceeding
Public Participation
- Public Adviser's Office
- Power Plant Siting Proceedings FAQs
- Power Plant Siting or Licensing Process
- Six Phases of the Power Plant Siting Process
- Public Participation in the Siting Process: Practice and Procedure Guide (PDF File, 3.3 mb)
- Summary of Typical Public Involvement Opportunities in Energy Commission Siting Cases
- Public Adviser's Presentations and Printed Materials
- Commission Siting Division
- Title 20
Calif. Code of Regulations - Acronyms and Definitions Used in Siting Cases
- Energy Commission News Releases
To subscribe to this proceeding's e-mail ListServer, enter the following information completely:
Willow Pass Generating Station Licensing Case, Docket # 08-AFC-6
Docket Number:
08-AFC-6
(Application For Certification)
Committee Overseeing This Case:
Karen Douglas, Commissioner
Presiding Member
(To be assigned)
Associate Member
Hearing Officer: Paul Kramer
Key Dates
- 10/08/2008 - Commission accepts Application as complete and "data adequate.".
- 6/30/2008 - Application for Certification filed with Energy Commission.
General Description of Project
Willow Pass Generating Station (Willow Pass) would be a new, approximately 550-megawatt (MW) dry-cooled, natural gas-fired electric power facility located in the city of Pittsburg in Contra Costa County, California. Development of Willow Pass would entail the construction of two generating units and ancillary systems including, adjacent electric and gas transmission lines, and water and wastewater pipelines. If approved, construction would occur over a 34-month period (from October 2009 through July 2012) and would cost approximately $585 million dollars. Commercial operation would commence in the summer of 2012.
Project Site: Willow Pass would be located two miles west of the Pittsburg city center within the existing Pittsburg Power Plant. Currently, the Pittsburg Power Plant site is occupied by seven generating units, three of which are still in operation. Willow Pass would occupy a 26-acre parcel adjacent to the existing generating units.
Generation Units: Willow Pass would consist of two power blocks, each containing one Siemens Flex Plant 10 (FP10) combined-cycle unit. The combined generating capacity of the two power blocks would be approximately 550 MW (net). The units are expected to operate at a 40 to 50 percent capacity factor and would use air-cooled heat exchanger (ACHE) technology to reduce water consumption.
Energy Commission Facility Certification Process
The Energy Commission's facility certification process carefully examines public health and safety, environmental impacts and engineering aspects of proposed power plants and all related facilities such as electric transmission lines, natural gas pipelines, etc.
The Energy Commission is the lead agency under the California Environmental Quality Act (CEQA) and has a certified regulatory program under CEQA. Under its certified program, the Energy Commission is exempt from having to prepare an environmental impact report. Its certified program, however, does require environmental analysis of the project, including an analysis of alternatives and mitigation measures to minimize any significant adverse effect the project may have on the environment.
For Questions About This Siting Case Contact:
For Questions About Participation In Siting Cases Contact:
Public Adviser
California Energy Commission
1516 Ninth Street, MS-12 Sacramento, CA 95814
Phone: 916-654-4489
Toll-Free in California: 1-800-822-6228
E-mail: PublicAdviser@energy.state.ca.us
News Media Please Contact:
Media & Public Communications Office
Phone: 916-654-4989
E-mail: mediaoffice@energy.state.ca.us